This article is for an owner or a developer with two or three plots and a spreadsheet. In 4sight's view, the spreadsheet is useful only after the nonnegotiable lines are binary. Each site needs its own evidence, whatever the team knows about the region.
Which conditions disqualify a site?
Write the conditions that remove a site before the scoring starts. Typical lines are a minimum utility capacity by a required date, credible diverse network access, hazard exposure the owner will accept, land control, a permitted use, secure access, and room for the first phase. Define them for the project. A checklist copied from another country is a different document. A condition the owner is willing to waive is a preference; score it later.
Disqualifying conditions and weighted criteria do different jobs
Scroll to see all columns
What does the dependency set include?
Score the whole dependency set. The attribute that favored the preferred plot is one input.
- Utility capacity, voltage, quality, route, redundancy, delivery program and commercial terms.
- Carrier availability, route diversity, latency needs and physical entries into the site.
- Flood, seismic, wind, heat, fire, contamination, neighbors and other hazards the project names.
- Water availability and restrictions where the cooling strategy needs water.
- Land, title, planning, environment, taxes, customs and authority approvals.
- Access, security, logistics, construction, workforce and local support.
- Building geometry, structure, plant areas, maintainability and expansion.
- Capital, operating cost, schedule, community exposure and reputation.
For an existing building, structure and space decide early. The banking site assessment records a bank building that failed the space and slab-loading test for an ANSI/TIA-942 Rated-3 objective, and 4sight recommended an alternate site. The rating structure behind such an objective is covered in the ANSI/TIA-942-C explainer.
What evidence does each input need?
Record the source, the date, the owner of the information, the confidence, the conditions and the expiry of each input. A utility expression of interest records interest. A contracted delivery commitment is a different document. A fiber route nearby still has to be proven as diverse service into the building. Two entries that share a bridge, a duct or a substation remain one route when the map shows two lines.
Where does site evaluation fail?
- A weighted score averages a failed power or network test into an acceptable total.
- An expression of interest from the utility is read as a delivery date.
- Two fiber routes on a map share one physical crossing.
- A hazard is scored from a regional map, without site evidence.
- Expansion is assumed without checking land, structure or utility headroom for later phases.
- Evidence carries no date, so an expired quotation or approval stays in the comparison.
When does due diligence start?
A shortlist precedes acquisition due diligence, which is a later gate. Legal, environmental, geotechnical, utility, network, planning, tax and other specialist investigations belong to the parties appointed for them. The owner accepts the risk only after those investigations close, or after it records the risk it is willing to carry. 4sight does not replace the conveyancing lawyer, the utility or the planning authority.
Which services apply?
The service is site selection. A project that has not yet chosen a market starts with strategy, feasibility and business case, and the article on what a feasibility study must show sets out that test.
Frequently asked questions
The most important data center site selection criteria are the ones the owner will not waive: utility capacity by the required date, diverse network access, acceptable hazard exposure, land control, permitted use, secure access and room for the first phase. These are tested pass or fail before any weighted score. Cost, access and other preferences are scored afterward.
A data center site should be chosen by weighted score only after every candidate has passed the disqualifying conditions. A weighted score can hide a failed test: a strong result on land price or access can average away a power date the project cannot miss. Weights should be agreed before any site is scored.
Diverse network access for a data center site is verified by tracing each carrier route physically into the building. Two routes that share a bridge, a duct or a substation remain one route, even when a map shows two lines. A fiber route nearby is not proof of service; the carrier's commitment and the physical entry points are.