4sight designed for a submarine cable operator in two phases against ANSI/TIA-942 Rated-3 requirements. Phase 1 fitted an immediate data center into the operator's existing building. Phase 2 designed a cable landing station on the ground floor with two data center floors alongside it, and 4sight managed the bid process for that phase.
The challenge
The operator needed an immediate data center, then a permanent landing station that could carry two data center floors. These were different projects with one rating target.
Phase 1 had to fit the existing architectural, electrical and cooling systems. Those systems limited design flexibility, and the timeline was tight. Phase 2 was a complete design covering structure, architecture, interior, power, cooling, network, security and safety. Construction prices were escalating while the design was prepared.
What 4sight did
- Recorded the existing architectural, electrical and cooling constraints and designed phase 1 inside them.
- Designed phase 2, the ground-floor landing station and two data center floors, against the Rated-3 requirements.
- Managed the bid process for phase 2.
The rating target was designed once, across the cable plant and the data center floors. A landing station drawn apart from the floors beside it leaves the Rated-3 requirement with no single arrangement to test.
What the owner received
Design information, requirements and standards-alignment documentation, and tender inputs for both phases. Phase 1 delivered a data center design inside the existing building rather than a design for a new shell. Cost control was treated as a design discipline throughout. The alignment documentation records how the design addresses the Rated-3 target; it is not a certificate.
Frequently asked questions
4sight designed for a submarine cable operator in two phases against ANSI/TIA-942 Rated-3 requirements. Phase 1 fitted an immediate data center into the operator's existing building. Phase 2 designed a cable landing station on the ground floor with two data center floors alongside it. 4sight managed the bid process for phase 2. The owner received design information, requirements, standards-alignment documentation and tender inputs for both phases.
The cable landing station design used ANSI/TIA-942 Rated-3 requirements as one rating target across both phases. 4sight recorded the existing architectural, electrical and cooling constraints and designed phase 1 inside them. Phase 2 covered structure, architecture, interior, power, cooling, network, security and safety. The alignment documentation records how the design addresses the Rated-3 target. It is not a certificate. Cost control was treated as a design discipline.
Another owner can copy the phased method 4sight used for this cable landing station. Fit the immediate data center inside the existing building's architectural, electrical and cooling limits. Design the permanent landing station and the data center floors to the same Rated-3 requirement, as one arrangement. Manage the bid process for that phase, and treat cost control as part of the design.